North Texas site prep guide
Shed & Metal Building Foundation Guide: Gravel, Concrete & Site Prep for North Texas
Most portable sheds do not need a concrete slab. A level gravel pad works fine. Steel buildings and garages over 24 feet wide usually require concrete with footings. This page gives the exact specs to use before you pour.
1) Portable sheds: gravel pad is fine
Portable skid sheds sit on grade and do not need slab footings. Keep the site within 2 inches of level across the full length so doors close correctly.
- Use 4 to 6 inches of compacted crushed limestone or 3/4 inch clean gravel.
- Extend the gravel pad 1 foot beyond the shed footprint on every side.
- Grade drainage to the edges at 1 percent minimum. Never let water pool under the building.
2) Steel buildings and garages: concrete with footings
Concrete is the standard for enclosed garages, overhead doors, and buildings over 24 feet wide. Slab size is always outside-to-outside frame dimensions.
When to pour 6 inches instead of 4
RV covers, enclosed garages, vehicle lifts, 12-gauge frames, buildings over 24 feet wide, and any site with expansive clay soil (common across North Texas) all require a 6 inch slab. If there is any chance you will add a vehicle lift later, pour 6 inches now — upgrading after the fact means breaking out and repouringthe floor.
Single leg buildings — 12' to 30' wide, legs ≤14'
- 4 inch thick slab minimum, 3,500 PSI concrete — 6 inches required for RV covers, enclosed garages, vehicle lifts, 12-gauge frames, or any building over 24 feet wide
- Plastic vapor barrier under slab
- 3/8 inch rebar on 18 inch grid throughout
- 12"×12" perimeter footings — industry standard square footer, runs wherever a base rail sits
- Texas Style buildings: footings under main structure AND under each lean-to; interior beams required under center section base rails
- Lean-tos: full concrete slab or runners required
- Anchor bolts: 1/2 inch diameter, within 6 inches of every post along sides and end walls
- Slab thickness can be increased per buyer request
Double leg & ladder leg buildings — 32' to 70' wide
Larger spans require a heavier footer and more rebar. Same slab spec as above except:
- Footings: 26 inches deep × 30 inches wide (engineered spec)
- Concrete: 3,500 PSI (exceeds 3,000 PSI engineering minimum)
- 8 continuous #4 rebar bars in each footing
- Anchor bolts: 1/2 inch diameter × minimum 7 inch A307 expansion anchors, within 6 inches of every post
- 32'–40' with legs ≤14': double leg frame (two galvanized square tubes welded together)
- 32'–40' with legs ≥15': ladder leg frame
- 42'–70': ladder leg frame regardless of height
- All 32'–70' wide buildings use ladder truss roof structure
| Width | Leg height | Frame type | Footer size | Rebar |
|---|---|---|---|---|
| 12'–30' | ≤14' | Single leg | 12"×12" square | 3/8" on 18" grid |
| 32'–40' | ≤14' | Double leg + ladder truss | 26" deep × 30" wide | (8) #4 continuous |
| 32'–40' | ≥15' | Ladder leg + ladder truss | 26" deep × 30" wide | (8) #4 continuous |
| 42'–70' | Any | Ladder leg + ladder truss | 26" deep × 30" wide | (8) #4 continuous |
Slab sizing rules
- Horizontal wall: slab equals exact outside-to-outside frame dimensions
- Vertical wall: slab equals exact frame dimensions — tin ledge adds 1.5" down and 1.5" out on all sides outside the slab edge
- Example: 30'×40' vertical wall building → 30.25'×40.25' actual footprint (slab + ledge overhang)
- Horizontal wall buildings have no tin ledge — slab equals exact frame size
Texas barn layouts require footings under the main structure and under each lean-to wherever base rails run. Interior beams required under center section base rails.
3) Garage door slab prep: two tray methods
Up to 30' wide, square tube method
- Use 2" x 6" board form, nominal 5.5" actual width
- Form length is 6" longer than door width
- Front notch is 2.5" x 3" so 2.5" square tube drops in cleanly
- Water ledge profile is 2.5" wide x 4" tall
- Include upright tab at far end for door track contact
- Recess is formed before pour, cannot be fixed after concrete sets
40' wide frame and larger span, ladder leg method
- Door tray runs full width of door opening
- Door track sits in 3" x 3" bottom channel behind ledge
- Concrete apron slopes from tray ledge to slab edge
- Slope runs across the entire opening width, not just edges
- Example: 12' door uses full 12' tray width with recessed track channel
Door tray and water ledge details must be formed before concrete pour. If this is wrong, door seal and tracking issues are expensive to correct later.
4) What you need before delivery day
Portable sheds checklist
- □ Site graded and level within 2 inches
- □ Gravel pad installed if soil is soft
- □ Access path 2 feet wider than building on each side
- □ Overhead clearance confirmed with our team
- □ Gate width at least 10 feet for most setups
Steel building checklist
- □ Slab poured and cured, 7 days minimum and 28 days full strength
- □ Slab dimensions verified outside-to-outside of frame
- □ Footers match frame type and width
- □ Garage door recess and tray formed correctly
- □ Vertical panel ledge accounted for on vertical wall buildings
- □ Utility conduit and other stubs set before pour if needed
- □ SkyTrak telehandler access confirmed if building is 32' wide or has legs 15' or taller
- □ Firm, level ground access for equipment (soft/muddy sites need gravel approach)
⚠️ SkyTrak Telehandler Requirement
A SkyTrak telehandler (6,000 lb capacity, 36-ft lift) is required for all 32' wide buildings — these use a ladder truss that requires overhead lift — and for any building with side legs 15' or taller. Make sure your site can accommodate the equipment before scheduling delivery.
5) Common mistakes that cause delays
- Pouring slab without the door tray or water ledge detail
- Sizing vertical wall slab wrong and forgetting ledge footprint growth
- Leaving gravel out of level so shed doors rack and bind
- Pouring too close to delivery date without minimum cure window
- Skipping access checks so truck cannot reach install location
Related planning links: delivery process, Texas shed permits guide, rent-to-own pre-approval.
Need a fast slab and site prep check?
Send us a photo of your site and we will tell you exactly what you need before delivery. It usually takes about 5 minutes.
Foundation and slab prep FAQ
Free 3D Configurator
Design Your Building in 3D
Configure your size, color, doors, and options. See pricing instantly — no salesperson required.
Open 3D Designer — It's Free →No account required · Takes 3 minutes · Get instant pricing
